Search history
Clear allSearch by image
XDrag and drop an image here or upload an image
Max 5MB per image
UploadSign In | Join
X Email Mobile
blister molding, spray gun + 1.2-meter shower hose +304 stainless steel base (brushed)
|
CN¥ 16.8 |
blister pack, spray gun + 1.2-meter shower hose +304 stainless steel base (black)
|
CN¥ 18.8 |
Qianyuanjian Plastic Shower Co., LTD 3yr.
Contacts:ChenSainan Chat
Mobile:86-15858915842
E-mail:452702132@qq.com
304 spray gun set, large quantity, contact for details.











New House Decoration Steps:
1. Preliminary design - 2. Main structure demolition and modification - 3. Water and electricity transformation - 4. Woodwork - 5. Tiling - 6. Painting the walls - 7. Kitchen and bathroom ceiling installation - 8. Cabinet installation - 9. Wooden door installation - 10. Floor installation - 11. Wallpaper pasting - 12. Radiator installation - 13. Switch and socket installation - 14. Lighting installation - 15. Hardware and sanitary ware installation - 16. Curtain rod installation - 17. Initial cleaning - 18. Furniture arrival - 19. Home appliance installation - 20. Home accessories
1. Preliminary Design: This stage primarily involves designing the space based on one's personal living habits. It is also essential to conduct a detailed measurement of one's own room. Do not be lazy; it is best to measure the space personally. The content of the measurement includes:
Clarify the area involved in the decoration process. Especially the tile area, the wall paint area, the wallpaper area, and the floor area;
Clear the main wall dimensions. Especially the wall dimensions that will be needed for furniture placement in the future.
2. Main structural alterations
Entering the construction phase, the main structural alterations are the first project to be implemented, which mainly includes demolition of walls, masonry, scraping of wall coatings, dismantling of heating systems, replacing plastic steel windows, and so on. Essentially, the main structural alterations are about setting up the framework of the construction site first.
3. Water and Electricity Renovation
Before the renovation of water, electricity, and plumbing, the basic structure should have been essentially completed. Between the renovation of water, electricity, and plumbing and the structural changes, some students may know that the first measurement of cabinets should be conducted. In fact, the so-called first measurement of cabinets does not contain any actual content, as the walls and floors have not been processed, and cabinet designers cannot provide specific design dimensions. They can only make some related suggestions based on the positions of the water inlets and cooker plugs reserved by the developers. This mainly includes:
Check if the position of the range hood outlet affects the installation of the range hood in the future.
Check if the water meter is in the right place.
Check the location of the upper water inlet to see if it is convenient for installing the sink in the future.
For the first measurement of the cabinet, students with a little experience can complete it on their own. After the water system renovation is completed, it is best to immediately do the bathroom waterproofing. Kitchen usually does not need waterproofing.
4、Woodworking
Woodworkers, masons, and painters are the 'three brothers' in the construction process, and their basic appearance order is: wood - tile - oil. The basic principle of appearance is - who is dirty goes first. "Who is dirty goes first" is also one of the basic principles that determine the order of home decoration, which I will mention later.
In fact, tasks such as installing a boiler pipe, decorating the ceiling, and applying plaster lines can be considered as a detailed part of the main demolition and modification in a sense. They are not in conflict with the transformation of water and electricity, and sometimes they need to be coordinated.
5. Tile Installation
In the process of "Tile Worker Number Two" work, the installation of the following three components is also involved:
The installation of the threshold stone and the marble window sill. The installation of the threshold stone can be completed together with the floor tile, or it can be done after the floor tile is laid. The installation of the marble window sill is generally done after the window casing is completed. The worker who installs the marble will prepare the glass sealant and seal the marble and the window casing with the glass sealant.
The installation of a floor drain. Floor drains are the first to appear in home decoration hardware, as they need to be installed together with the tile. Therefore, students should buy floor drains early when they start shopping for construction materials.
The installation of a range hood. After the kitchen wall and floor tiles are laid, it is time to consider installing a range hood.
The second carpenter" leaves the field, and at this time, you can arrange for the cabinet to measure for the second time. To be precise, after the kitchen wall tiles are pasted and the cooker hood is installed, you can arrange for the cabinet to measure for the second time.
Paint the walls
Oil worker Lao San" enters the scene, mainly to complete the work of wall base treatment, painting, and painting on furniture made by "Woodworker Lao Da". Students who are preparing to paste wallpaper only need to let "Oil worker Lao San" do the base treatment on the wall where they plan to paste wallpaper. As for whether to leave the final coat of paint, personally, I feel that there is no need to be too serious about this question. According to my experience in decorating, leaving one coat of paint is not very significant, because the subsequent operations are not dirtier than painting.
7、Kitchen and Bathroom Ceiling
The cabinet ceiling is the first step in the installation process, still continuing to 'pack' the home. While the kitchen and bathroom ceilings are being installed, the kitchen and bathroom moisture-proof downlights and exhaust fans (bathroom heaters) should have been purchased. It is best for students to install the kitchen and bathroom downlights and exhaust fans (bathroom heaters) at the same time, or leave the wire ends and open holes.
8、Cabinet Installation
After the ceiling installation is completed, it's possible to arrange for the cabinet installation to be done at the customer's home. If everything goes smoothly, it should be possible to finish in one day. At the same time, the sink (which does not include the plumbing) and the gas stove will also be installed. It's best to coordinate with the property management to have the gas line opened before the cabinet installation, as the gas stove needs to be tested after it's installed.
9. Wooden Door Installation
The next day after the cabinet installation, after the wood door measurement was completed more than a month ago, now it can be scheduled for installation. If everything goes well, it will take only one day. During the door installation, hinges, door locks, and floor suction should also be installed. The classmates should prepare the relevant hardware in advance.
If you want the wood door manufacturer to install the window trim and door frames, measure them when the wood door manufacturer measures the door, and install them on the same day as the wood door. At the same time, it is recommended to postpone the installation of the marble window sills to after the window trim installation.
Note: The production cycle for wood doors is generally one month, so in order to ensure a tight schedule, it is best to have the wood door manufacturer come to measure the door opening dimensions as soon as the main structural alterations are completed. Regarding the treatment of the door openings, it is important to note that if the heights of the door openings in the home are not uniform, they need to be made to be the same height – it looks better.
Floor Installation
The next day after the installation of the wooden door, the floor can be installed. If everything goes smoothly, it will also take one day. Here are a few issues to be aware of when installing the floor:
1. Before the floor installation, it is best to have the manufacturer come to the site to measure whether the ground needs leveling or local leveling. Some decoration companies or renovation teams may suggest that the ground be leveled or locally leveled, but it should be based on the actual survey by the floor manufacturer.
Before installing the floor, make sure the floor surface to be laid is clean and dry. Therefore, do not use water during the cleaning process.
3. When installing the floor, if possible, the cutting of the floor should be done in the hallway. This issue has also been discussed in forums before. Some students believe that cutting the floor in the hallway pollutes the common area, which is immoral. My idea is to clean up after the work is completed, which is not a big deal. Cutting the floor inside the room can cause serious pollution to the walls. Similar to the cutting of the synthetic stone countertop of the cabinet, I believe students who have decorated have some experience with this.
(Eleven)Wallpaper Tiling
The next day after the floor installation, the house will be cleaned up, and the wallpaper can be pasted. If everything goes well, it will take the same amount of time. If possible, the floor should be protected on the day of wallpaper pasting; if not, it's okay to leave the task of cleaning up the residual wallpaper glue on the floor to the initial cleaning service. Before pasting the wallpaper, the wall surface should be as clean as possible, with "nothing at all".
(Twelve)Radiator Installation
The following day after the wallpaper is laid, students who have replaced the radiator or dismantled and modified it can safely hang the radiator on the wall. It takes the same amount of time.
Wooden doors – flooring – wallpaper – radiators. This is a widely recognized correct installation sequence. Installing the wooden doors first ensures that the skirting boards of the flooring can closely fit the door casings. Wallpaper is installed later because the flooring installation is dirty and dusty, which can seriously pollute the wallpaper. This time, the principle of "who is dirty goes first" is used again. Finally, the radiators are installed because only after the wallpaper on the walls is laid can the radiators be installed.
Thirteen) Switch and Socket Installation
Students should have a detailed understanding or record of the number and location of switches and sockets in each room of their homes, especially for those who are going to paste wallpaper. Sometimes, the wallpaper workers are irresponsible, and they will just spread the wallpaper without marking the positions of switches and sockets with a wallpaper knife. Therefore, it is still necessary for students to have a clear understanding in their minds.
(十四)Lamp Installation
Installing the lights was nothing special. Once the lights were installed, the house lit up, and we said goodbye to the intense glare of the 100-watt incandescent bulbs during the renovation period—it felt great.
(十五)五金洁具安装
The plumbing fittings, bathroom hooks, toilets, clothes racks, etc. that I had purchased earlier were all installed at once. After the "big items" were installed, the house was still very "cold". It wasn't until the lighting and hardware fixtures were installed that the house came to life. It really came to life. It's not an exaggeration to say that the first time you turn on the tap and watch the water "gurgle" out, you will feel very happy; the first time you use the new toilet at home, you will feel a sense of achievement. By the way, I also gave it a good name - "Virgo".
(十六)安装窗帘杆
The installation of the curtain rod marks the basic completion of home decoration.
(十七)拓荒保洁
Before the initial cleaning, do not install curtains, as the reminder in the post "Explaining Curtains" reminded everyone. During the initial cleaning, there should be no furniture or unnecessary electrical appliances in the house, and as many "flat surfaces" as possible should be maintained to ensure that the initial cleaning can be thoroughly cleaned.
Furniture Arrival
Regarding the time to purchase furniture, my suggestion is to wait until the water, electricity, and plumbing renovations are completed. Only then will we have a rough idea of the basic size range for furniture. Therefore, it's not necessary for some students to rush to book their furniture before the decorating work has even started.
Home Appliance Arrival
By this time, the household appliances should be set up, installed, and ready for moving in!
:"(二十)Home Decor
Home accessories are the final step in home decoration, and have now shifted from construction to decoration, including the installation of curtains, which all fall under the home accessories category. When it comes to buying curtains, it's best to do so after the furniture is ordered to avoid any style conflicts. Home accessories also include the possibility of purchasing some green plants, hanging wall art, and displaying crafts, and so on and so forth... In short, once you move in, you can freely express yourself.